Showing posts with label Constuction. Show all posts
Showing posts with label Constuction. Show all posts

Wednesday, July 6, 2011

Drive In Cooler

The other massive project we tackled while we were working to get the brew house up and running was construction of our walk in cooler.  We pretty much bought the largest cooler we could afford and that would fit into our space.  The reason we wanted a larger cold space is that since we are self-distributing our beers we will be storing them until on site until we deliver them to retail accounts.  Since we won’t be shipping our kegs off to a distributor in bulk once they are packaged we wanted a large enough space to keep all our beer stored cold.  We also wanted to have enough space to properly age some kegs and / or barrels.  

We ended up getting a used box that was 36 feet long, 18 feet wide and 16 feet tall.  It’s about 650 square feet of cold box goodness.  We realized once it was up that it was larger than the last apartment my wife and I shared in the city by about 150 square feet—and we lived there for five years.  It should be a good home for our kegged beer, hops and anything we plan to age.  Since we bought it used, it was delivered to us as a stack of loose panels in the back of a tractor trailer.


It took us about three hours to get the massive 8x8 door and about forty 16x4 panels unloaded by hand off the truck.  At least this gave the driver a chance to take a nice afternoon nap in the cab.   


As you can see from the photo organizing the panels happened another day. Getting the box built was one of the more difficult things we had to do.  We were told the box is self supporting and that each panel locks into the one next to it.  It’s true that the panels lock into one and other, but that’s only true if the locks work.  It also seemed that it would be better to add some type of support to hold the roof up.  This ended up taking the most time.  

We started by getting the three walls built, then we planned to add the roof, then the front with the door.  The cold box doors supported by our warehouse walls were not that difficult to get up, but the free standing walls were a little more difficult. 


Because the panels are 16 feet tall they were difficult to stand up and get into place without tipping over.  Again, the forklift was crucial in getting these into place. 


After getting the outer walls built we lifted the ceiling panels on with the forklift.   We chose to support them with threaded rod and unistruts from the existing roof but this took a while

.  


Once we finally got the ceiling on, we needed to cut a few panels to build in a space for the door then hang the surprisingly heavy sliding door on the tracks.  After that we brought  in a refrigeration guy to hook the cooling unit up and we were on our way. Two quick coats of white paint and the box was finished.  

Monday, May 9, 2011

Quick Update

We were able to track down a survey of the property from a company in Long Branch that did some work on this building in the early 1980s.  They were kind enough to give me a copy of what they had so that I could use that for the basis of our Minor Site Plan Application.  The engineers based their site plan on the survey data from that drawing and laid out where on the property we intend to install the unit.  I got the drawing from them yesterday and submitted the application with some pictures of the property and some data on the chiller itself.  I also found out that the meeting was moved from May 23 to June 8, so we won’t know officially if we can install it until two weeks later. 

We are still waiting for the fire suppression (sprinkler system) permit but these are the last two items we need from the town…for now. 

The FlowCrete guys are scheduled to start installing the floor covering tomorrow and the plumber is coming by the go over the work plan for the next few weeks.  We should be in a position to move the equipment into its final location this weekend and the electrician is planning to finish the main service by Monday.

We are still working to finalize the date, but the team from DME coming down to help install the equipment will probably be here at the end of the month.  We should be able to get the brew house functioning over the ten days they are here.

The condenser unit for the cooler arrived a few days ago and the box itself should be here early next week.  By then the brewing equipment will be out of the way so we can build that in place later next week.  The only piece of equipment we are waiting for is the keg washer and our 1/6 kegs—both of which should be here within a few weeks.